Report summary (milestones in yellow; underscores means programmed activity; percentages estimate the work done):
 
1998 budget activities Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
T1.1 acustic units 30% ___ ___ ___ ___ 50% ___ ___ 80% 85% 86%
T1.2 cheap spotting ___ ___ ___ ___ ___
T1.3 on-line adapt. ___ ___ 50% ___
T2.1 dialogue study ___ ___
T2.2 prototype impl. ___ 15% 40% 60% 70% 85% 94% 98% 99% END
T2.3 database coll. ___ ___ ___ 30% 70%
T2.4 prototype impr. ___ 20% ___ ___
T3.1 CARITRO 60% 75% 85% 95% 97% END
T3.2 ALCEO ___ ___ ___ ___ ___ ___
T3.3 switch IRST  15% 20% 40% 60% 80% 90% 92% 96% 99% END ___ ___
T3.4 database (ELRA) ___ ___ ___ ___ ___ ___ ___ ___
other activities
benchmark CSELT 60% END
ATLANTIS-VOX X X X X X X XXX GO
APT XXX X X X X END
FONDAZIONE CARITRO ??? ? ? GO
ERICSSON X X
incoming money (M lit)   93.75 11.4 200
VOX APT FC
 
Report summary (milestones in yellow; underscores means programmed activity; percentages estimate the work done):
 
1999 budget activities Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
T1 - Tecnologia
T1.1 strumenti 10% 30% 50% 80%
T1.2 prototipo con API 25% 50% 80% 90% 100% END
T1.3 irrobustimento 5% 10% 15% 30% 30% 35% 40% ___ ___ ___ ___ ___
T2 - progetto VOX
T2.1 generatore applicazioni END 10% 20% ___
T2.2 motore dialogo 20% 70% END 10% 20% ___
T2.3 integrazione 5% 15% 90%
T2.4 raccolta database 0% 0% ___ ___ ___
T2.5 documenti 10% 30% ___ ___ ___ ___
T3 - progetto ATP
T3.1 definizione funzionalita` 30% 50% 50%
T3.2 implementazione prototipo  10% 15% 15% 20% 30% 40% 40% ___ ___ ___ ___
other activities
incoming money (M lit) 150
VOX ...
 